The notice of readiness (NOR) is the small document with the large consequences. It is the master’s written notice to the charterer, or the charterer’s agent, that the ship has arrived at the agreed place and is ready in all respects to load or discharge. From that notice, after any agreed turn time, laytime starts to run. Get it wrong and the owner may lose a week of demurrage.
Three conditions for a valid NOR
1. The ship has arrived. Where “arrived” is depends on the charter. Under a port charter the ship has arrived when she is within the port limits at the place where waiting ships usually lie, at the charterer’s immediate disposition. Under a berth charter she has arrived only when she is at the berth, unless a clause such as “WIBON” (whether in berth or not) or 1 SB 1 SP shifts the waiting risk to the charterer.
2. The ship is physically ready. Holds clean, dry and suitable for the cargo, hatches workable, cranes operational, ballast able to be discharged. For a fertiliser cargo such as urea in bulk, “clean” means free of residues of the previous cargo, rust scale and moisture; a failed hold inspection makes the NOR invalid until the holds pass.
3. The ship is legally ready. Free pratique, customs clearance and any documents required by the port. Many charters allow NOR to be tendered “whether in free pratique or not” (WIFPON) and “whether customs cleared or not” (WCCON), which removes those two formalities as obstacles.
What the charter party says about timing
Typical clause: “Notice of readiness to be tendered during office hours Monday to Friday 09:00–17:00, Saturday 09:00–12:00. Laytime to commence at 14:00 if NOR tendered before noon, and at 08:00 next working day if tendered in the afternoon.” Outside those hours NOR is treated as tendered at the next opening. A NOR tendered before the laycan may be valid, but laytime does not start before the first layday unless the charterer agrees to start earlier (“time used before laytime commences to count”).
The classic mistake: an invalid NOR is not cured by waiting
If the ship was not ready when NOR was tendered (holds rejected, ship not yet arrived), the notice is invalid, and under English law a subsequent readiness does not automatically revive it. The master must tender a fresh NOR. If nobody does, laytime may only start when loading actually commences, and all the waiting time falls on the owner. Prudent masters therefore tender NOR again after every event that could have affected readiness and keep the acceptance by the agent on file.
What the charterer should check
The charterer’s operator checks the NOR against the statement of facts: time and place of tendering, whether the ship was actually at the anchorage or berth, hold inspection results, free pratique. Every hour between an accepted NOR and the actual start of loading is potentially the charterer’s time. Disputing a premature NOR is legitimate; ignoring a valid one is expensive.
NOR under time charter
Under a time charter there is no laytime, so NOR at the ports does not matter commercially; the equivalent moment is the notice of delivery, when the ship is placed at the charterer’s disposal and hire starts. The same readiness questions (holds, documents) determine whether delivery is valid.
Frequently asked questions
Who tenders the notice of readiness?
The master, usually through the ship’s agent, to the charterer or the charterer’s agent, in the form and hours the charter party prescribes.
Does laytime start immediately after NOR?
Not usually. The charter party provides a turn time, for example laytime commencing at 14:00 for a morning NOR or at 08:00 the next working day for an afternoon NOR.
What happens if the NOR is tendered too early?
If the ship is not yet arrived or ready, the NOR is invalid. A new NOR must be tendered once the ship is ready; otherwise laytime may not start until loading begins.
What does WIBON mean?
“Whether in berth or not”: NOR may be tendered from the waiting place if the berth is occupied, so that waiting time counts as laytime.