PWWD SHINC

The loading rate that defines how much time the charterer has before demurrage starts.

2.000 MT PWWD SHINC

What it means

Per weather working day, Sundays and holidays included. Divide the cargo quantity by the rate and you have the allowed laytime in days. Weather that actually stops the work does not count; Sundays and holidays do. Laytime only starts once a valid notice of readiness has been tendered and the notice time has run.

The question underneath

When exactly does the clock start, when does it stop, and who bears the hours in between?

Where it goes wrong

Notice of readiness is tendered while the holds are not yet clean. The notice is invalid, laytime never started, and a week later everyone is arguing about a six-figure demurrage claim.